Radiological Commissioning of the LCLS-II CW Superconducting Linac: Shielding Validation and Radiation Monitor Performance

Oct 20, 2026, 11:15 AM
20m
IBS Science Culture Center, Daejeon, Korea

IBS Science Culture Center, Daejeon, Korea

Expo-ro, 55, Yuseong District, Daejeon, Korea

Speaker

Thomas Frosio (SLAC)

Description

The Linac Coherent Light Source II (LCLS-II) at SLAC is a continuous-wave (CW) superconducting radiofrequency (SCRF) electron linac that accelerates electrons to about 4 GeV at MHz repetition rates, with a design beam power of 120 kW and a maximum credible beam power of 1.2 MW. Radiological commissioning advanced through staged beam destinations: halo collimators along the linac, the Beam Switch Yard Dump (BSYD) embedded in the 17 m iron muon shield wall between the linac and the undulators, and the electron beam dumps (EBDs) that follow the soft and hard X-ray undulators. At each stage, prompt and residual dose rates were measured, and passive shielding and active monitoring systems were validated.
All prompt dose rates at occupied service-area penetrations remained below the 5 μSv/h design limit at every beam power commissioned so far, up to about 19 kW. The highest readings stayed about a factor of two below that limit. FLUKA Monte Carlo calculations reproduce the measured prompt and residual fields, in most cases within a factor of two and at several locations within a few tens of percent. This shielding benchmark directly supports the radiation-protection framework for the High-Energy (HE) upgrade to 8 GeV, now being installed.
Beam-loss and radiation monitor commissioning produced several transferable findings. CIVIDEC B4 polycrystalline diamond Point Beam Loss Monitors (PBLMs) exhibited signal decay with an approximately 18-hour half-life after beam-off due to charge trapping, rendering them unsuitable for machine protection; single-crystal B1 replacements respond proportionally and promptly to beam loss with no extended decay. Thick targets attenuate the Cherenkov signal from quartz Long Beam-Loss Monitor (LBLM) fibers by more than an order of magnitude. Oxygen-15 activation of dump cooling water, read by a Residual Dose Monitor (RDM) at the heat exchanger, provides a real-time proxy for the power delivered to the dumps, the onset delay and the decay constant being set by the coolant transit time and by the short-lived activation products. Dark current from SCRF cryomodules produces a persistent radiation background, and characterizing how these fields propagate through the linac tunnel is essential for reliable interpretation of the fixed monitor baselines.

Topics T1. Source terms, new accelerator facilities and related topics

Author

Thomas Frosio (SLAC)

Co-authors

A. S. Fisher Andrew Rosenstrom Henry Brogonia Jan Blaha (SLAC National Accelerator Laboratory) Jim Allan Johannes Bauer Mario Santana-Leitner Qi Ding Sayed Rokni